Officials announced full closures of interstates, ramps, bridges and primary roads, and lane closures at the bridge-tunnels and the Berkley, Coleman, High Rise and James River

Richmond, VA – VDOT officials say that this is the full list of closures:

Bridges and Tunnels:

  • Hampton Roads Bridge-Tunnel, I-64:
    • Mobile, single-lane closure eastbound Jan. 31 from 9 p.m. to 5 a.m.
  • Monitor-Merrimac Memorial Bridge-Tunnel, I-664:
    • Alternating, single-lane closures southbound Jan. 28 to Feb. 1 from 9 p.m. to 5 a.m. 
    • Single-lane closure southbound Jan. 29 from 9 p.m. to 5 a.m. 
    • Alternating, mobile, single-lane closures northbound Jan. 30 from 9 p.m. to 5 a.m.   
  • James River Bridge, Route 17: 
    • Single-lane closures in both directions: 
      • Jan. 28-31 from 9 p.m. to 5 a.m. 
      • Jan. 29 to Feb. 1 from 9 a.m. to 3 p.m. 
      • Feb. 1 from 7 p.m. to 1 a.m. 
    • Brief, intermittent stoppages in both directions: 
      • Jan. 28 to Feb. 1 from 9 p.m. to 5 a.m. 
      • Jan. 29 to Feb. 1 from 9 a.m. to 3 p.m. 
    • Full extended closure of the James River Bridge from 1 a.m. on Feb. 2 through 5 a.m. on Feb. 6. 
  • George P. Coleman Memorial Bridge, Route 17:
    • Single-lane closure and brief, intermittent stoppages northbound Jan. 28 from 7 a.m. to 7 p.m. 

Elizabeth River Tunnels (Downtown/Midtown Tunnels):

  • Information from Elizabeth River Tunnels for maintenance schedules and lane closures on the Downtown Tunnel (I-264), Midtown Tunnel (U.S. 58) and MLK Expressway (Route 164). 
  • Hampton:
    • Brief, intermittent stoppages on I-64 east between the Hampton River Bridge and Mallory Street (exit 268) Jan. 29-30 from 10 p.m. and 5 a.m. 
    • Brief, intermittent stoppages on I-64 west between the Hampton River Bridge and LaSalle Avenue (exit 265): 
      • Jan. 31 from 10 p.m. to 5 a.m. 
      • Feb. 1 from 10 p.m. to 1 a.m. 
    • Long-term, continuous single-lane closure on I-64 in both directions, reducing travel lanes from three to two lanes between Settlers Landing Road/Woodland Road (exit 267) and LaSalle Avenue (exit 265), with I-64 west traffic shifted to the I-64 east lanes. 
  • Norfolk:
    • Full closure of the on-ramp from Granby Street to I-64 east Jan. 28 to Feb. 2 from 7 p.m. to 5 a.m. 
    • Full closure of the off-ramp from I-64 east to I-564 west/Granby Street (exit 276A) Jan. 28 to Feb. 2 from 7 p.m. to 5 a.m. 
    • Full closure of the on-ramp from Tidewater Drive south to I-64 east Jan. 28 to Feb. 2 from 8 p.m. to 5 a.m. 
    • Full closure of the off-ramp from I-64 east to Tidewater Drive north (exit 277B) Jan. 28 to Feb. 2 from as early as 8 p.m. to 5 a.m. 
    • Full closure of the on-ramp from Tidewater Drive north to I-64 east Jan. 29 to Feb. 2 from 8 p.m. to 5 a.m.  
    • Brief, intermittent stoppage of the on-ramp from Little Creek Road to I-64 east Jan. 29 to Feb. 2 from 11:59 p.m. to 4 a.m.  
    • Full closure of the ramp from I-564 east to I-64 east Jan. 30 to Feb. 1 from 9 p.m. to 5 a.m. 
  • Norfolk, Reversible Roadway:
    • Full closure in both directions:
      • Jan. 28 to Feb. 1 from 8 p.m. to 3 a.m. 
      • Jan. 29 to Feb. 2 from 9:30 a.m. to 12:30 p.m. 
Total
0
Shares
Previous Article

VDOT officials announced that highway work is scheduled in the Culpeper District during this week